Start With the Protection Objective
Begin by identifying the circuits and equipment that need protection: utility incomers, transformers, bus sections, feeders, motors, generators, or tie breakers. For each, describe the abnormal conditions the relay must detect and the intended response. A protection study, one-line diagram, and coordination requirements provide a stronger basis than naming a relay model alone.
Relay scope depends on the equipment and system voltage. A low-voltage assembly may use electronic trip units or protective relays, while medium-voltage switchgear commonly uses dedicated relays and instrument transformers. UL 891 switchboards, UL 1558 low-voltage switchgear, and medium-voltage equipment are distinct categories; verify the applicable construction and protection requirements for the project.
Define Functions and Coverage
List required functions by circuit and application rather than assuming every relay needs the same feature set. Depending on the design, functions may include phase and ground overcurrent, differential, undervoltage, overvoltage, frequency, reverse power, or thermal protection. Confirm whether the relay must provide backup protection, breaker failure logic, reclosing, or zone-selective coordination.
Function selection must follow the system study and equipment duty, not a generic checklist. Specify which protection elements are required, which are intentionally disabled, and any alarm-only conditions. Identify whether metering, event records, oscillography, or disturbance data are needed, and whether these functions belong in the relay or another control device.
Specify Sensing Inputs
Provide the expected current- and voltage-sensing arrangement for each relay: CT locations, ratios, polarity, secondary ratings, and whether residual, neutral, or core-balance sensing is required. For voltage inputs, state the source and transformer configuration, nominal secondary values, grounding arrangement, and any need to detect loss of potential.
Input compatibility is a design constraint. The responsible engineer should confirm instrument-transformer accuracy, burden, insulation, fault duty, and relay input ratings together. Identify existing site CTs or VTs only when their data and condition are documented; otherwise, state whether new sensing components are included in the equipment scope or furnished separately.
Describe Trip and Control Interfaces
For each protective function, identify the breaker or device to be tripped and the required trip path. Clarify whether the relay operates a shunt-trip coil, a breaker trip circuit, an interposing relay, or a specified control scheme. Provide control voltage, trip-coil data, contact requirements, and any required supervision or trip-circuit monitoring.
Define how the relay interfaces with breaker status and control circuits. Typical points to resolve include auxiliary-contact inputs, close permissives, lockout functions, local and remote trip sources, and trip-circuit isolation. The final design should account for the breaker manufacturer's interface data, control power availability, wiring segregation, and project-specific fail-safe requirements.
Plan Communications and Data
State whether relays must communicate with a plant control system, SCADA, or a protection network. Identify the required protocol, physical media, port arrangement, network topology, addressing responsibility, and whether communications are for monitoring, control, or both. Do not assume a protocol or port is standard across relay models or equipment configurations.
List the data points that matter to operations: relay targets, measured values, breaker position, alarms, event records, and time-stamped sequence-of-events data. Confirm time-synchronization method, cybersecurity or access-control requirements, and who supplies switches, gateways, fiber, and configuration. The equipment quote should distinguish included relay interfaces from external network infrastructure.
Assign Settings and Coordination Work
Relay settings should be developed from the approved protection and coordination study by the party responsible for system protection. Identify who provides settings files, who reviews them, and whether relay programming, loading, or functional verification is part of the manufacturer's scope. Do not treat example values or factory defaults as approved project settings.
The study should reflect actual utility fault data, transformer characteristics, conductor and equipment limits, grounding, and upstream and downstream protective devices. Clarify whether settings must be delivered as a file, entered in the relay, or both, and identify required revision control. The responsible engineer, utility, and AHJ should review applicable design and approval matters.
Coordinate Physical and Application Details
Relay selection and panel arrangement affect more than the device cutout. Provide preferred relay models only when they are approved for the application, along with mounting, display access, rear or front wiring needs, terminal preferences, and any required test switches. Confirm available panel space and maintainability requirements before finalizing the arrangement.
For a custom assembly, relay placement, wiring, terminal blocks, and test facilities can be coordinated with the switchgear design. State whether protection is required on each breaker, shared across a lineup, or integrated with control equipment. Identify environmental conditions and any project-specific requirements for labels, drawings, spare inputs, or future circuit expansion.
Prepare Information for a Complete Quote
A quote-ready package should include the one-line diagram, equipment type and voltage class, circuit schedule, fault and load data, protection study or function list, instrument-transformer information, breaker control details, and communications requirements. Include the intended relay settings responsibility and requested documentation. Note any owner standards or approved-device constraints that could affect configuration.
Also identify quantities, lineup arrangement, delivery location, schedule needs, and scope boundaries for field wiring, network hardware, commissioning, and testing. The manufacturer builds new equipment in the United States with American components, offers custom fabrication, and ships nationwide; project-specific lead time and included services should be confirmed in the quotation.
Verify Scope Before Release
Before releasing a design, reconcile the relay function list, sensing diagrams, trip schematics, communications points, and settings records against the latest one-line and coordination documents. Resolve discrepancies in CT polarity, trip voltage, breaker contacts, or protocol requirements early; these details can change both the equipment configuration and project interfaces.
Confirm who approves relay models, drawings, settings, and final wiring, and establish the required submittal sequence. Equipment documentation can describe supplied components and interfaces, but it does not replace the protection engineer's study or site-specific commissioning plan. Have the responsible engineer, utility, and AHJ check requirements where their review applies.