Start with the system’s actual voltage conditions
A 35 kV designation describes a nominal system class, not the maximum voltage an assembly can withstand in service. Identify the highest system voltage expected at the connection point, including utility operating limits and credible switching conditions. The equipment’s rated maximum voltage must suit that value; nominal voltage alone is not a sufficient selection basis.
Ask the utility or responsible engineer to confirm whether the service is nominally 34.5 kV, 35 kV, or another value, and document frequency, phase arrangement, and grounding method. These details shape the equipment class and insulation coordination. A quote should state the proposed ratings and assumptions for review, rather than infer them from a project label.
Coordinate insulation with system exposure
Insulation selection involves more than choosing an equipment voltage class. The engineer should establish required power-frequency withstand and impulse withstand levels, considering the system’s highest voltage, lightning exposure, switching surges, and protective-device characteristics. Confirm the applicable standards and project criteria for the intended installation and service conditions.
Surge arresters, cable terminations, bus supports, and other connected components need compatible insulation levels and clearances. Their coordination should be assessed across the complete connection, not as isolated catalog values. Provide the manufacturer with the specified insulation levels and interface requirements; the responsible engineer should verify the proposed arrangement against utility criteria and the site’s surge-protection design.
Establish short-circuit and grounding requirements
Available fault current and clearing time affect the required interrupting and withstand capabilities of switching devices and assemblies. Request current utility data or a documented system study, including X/R ratio when relevant to the specified duty. Identify normal, contingency, and future conditions that could change fault levels, and have the engineer determine governing values.
Grounding method is equally important at 35 kV. Solidly grounded, resistance-grounded, and ungrounded systems can produce different ground-fault magnitudes and overvoltage behavior. State the grounding arrangement, ground-fault protection approach, and required equipment grounding provisions. The selected switchgear configuration and ratings must be checked against these system conditions, not assumed from voltage class.
Choose a configuration around the one-line
The project one-line diagram clarifies whether the lineup needs incoming and feeder positions, bus sectionalizing, tie switching, metering, or transformer connections. Specify the operating sequence and identify which devices must isolate, interrupt load, or clear faults. Switches, circuit breakers, fuses, and associated controls serve different duties; the engineer should define the required functions.
Also document lineup arrangement, cable entry and exit directions, termination space, bus connections, and provisions for future circuits. Indoor or outdoor placement, access clearances, maintenance approach, and adjacent equipment interfaces can constrain the design. A manufacturer can develop a custom-fabricated configuration from these project inputs, subject to engineering review and applicable requirements.
Define switching, protection, and control needs
List the protective functions and relay interfaces required for each source and feeder, such as overcurrent, ground-fault, or transformer protection where applicable. Provide instrument transformer ratios and accuracy needs, control voltage, trip and close logic, communications protocols, and any interlocking requirements. These details should follow the protection study and the owner’s operating philosophy.
Clarify whether remote operation, local indication, event recording, or integration with plant controls is required. Identify the signals exchanged with upstream and downstream systems, along with any cybersecurity or network constraints. Do not treat these as standard features without confirmation: the quote should identify included devices, wiring, and interfaces for the specific build.
Account for site and installation conditions
Environmental conditions influence enclosure and construction choices. Report indoor or outdoor location, ambient temperature range, altitude, humidity, contamination, corrosive exposure, seismic criteria, and any unusual vibration or flooding risk. Confirm the applicable enclosure and environmental requirements with the engineer and AHJ; suitability depends on the actual site and specified construction.
Installation logistics matter as well. Provide available room dimensions, floor loading limits, cable trench or duct locations, access routes, lifting constraints, and required working clearances. State whether the lineup must fit through existing doors or be shipped in sections. These constraints can affect compartment layout, shipping splits, field connections, and the scope of installation work.
Verify standards, interfaces, and scope boundaries
At 35 kV, specify medium-voltage equipment standards and ratings appropriate to the design. UL 891 applies to low-voltage switchboards and UL 1558 to low-voltage switchgear; neither is a 35 kV equipment standard. Do not assume a low-voltage listing or product description establishes suitability for medium-voltage service.
Identify the governing project specifications, utility requirements, applicable codes, inspection expectations, and documentation deliverables. Confirm whether the scope includes relays, metering, terminations, surge arresters, commissioning support, or field services. A proposed build’s approvals and construction details must be verified for that specific configuration, rather than presumed from another voltage class.
Prepare a complete request for quotation
A useful RFQ package includes the one-line diagram, load and feeder schedule, nominal and maximum system voltage, insulation levels, grounding method, fault-study data, protection requirements, and site conditions. Add layout drawings, cable details, preferred operating sequence, utility standards, and the required delivery location. Mark unresolved inputs clearly so they can be reviewed before design release.
The U.S. manufacturer builds new switchgear and distribution equipment with American components, offers custom fabrication, and ships nationwide. For a 35 kV quotation, request a written equipment description, rating schedule, stated assumptions, exclusions, and submittal requirements. The responsible engineer, utility, and AHJ should review the design and interfaces before procurement and installation.