Start with the Existing Lineup
Identify the equipment the new lineup will replace or connect to. Share manufacturer, catalog or style number, serial number, nameplate photographs, and approximate installation date when available. Record whether the equipment is a switchboard, low-voltage switchgear, or medium-voltage assembly; these categories have different construction and application requirements.
Note the lineup location, number of sections, approximate dimensions, and which sections are in scope. If the existing identification is incomplete or unreadable, say so rather than guessing. A quote can begin with partial records, but unknowns should be marked for field verification before dimensions, interfaces, and configuration are finalized.
Send Drawings and Field Records
Useful documents include one-line diagrams, front elevations, floor plans, wiring diagrams, connection details, and prior modification records. Include revision dates and identify which drawings reflect current conditions. Photos of nameplates, bus connections, cable entries, barriers, and surrounding obstructions can help clarify information that a drawing omits.
For older installations, drawings may not match the equipment as it stands today. Flag field changes, abandoned circuits, replaced breakers, or added control devices. If records are unavailable, indicate whether a site survey, measured dimensions, or additional photographs can be arranged; do not treat estimated dimensions as verified fabrication data.
Define Electrical Requirements
Provide system voltage, phase and frequency, available fault-current information, grounding arrangement, and the source and load configuration. Identify the main device and feeder quantities, protective-device types, continuous current needs, and any known coordination or metering requirements. Include the applicable project specifications and requested standards so the equipment type can be evaluated correctly.
Confirm the equipment classification and intended application with the responsible electrical engineer. UL 891 applies to switchboards; UL 1558 addresses low-voltage switchgear. Medium-voltage equipment requires a separate application review and is not covered by UL 891. A particular build’s ratings, construction, and approvals must be established for that project, not assumed from the old lineup.
Map Physical and Electrical Interfaces
A retrofit depends on how the new assembly will meet existing conductors, bus, raceways, and adjacent equipment. Provide bus dimensions and orientation if documented, conductor material and size, cable count, entry direction, termination space, and connection locations. Identify whether the design must align with existing bus or transition through a separately engineered connection.
Share room clearances, aisle access, floor openings, housekeeping-pad details, overhead restrictions, and the route from delivery point to installation location. Note whether the existing footprint must be retained or whether layout changes are possible. These details affect section arrangement and installation planning; compatibility should be verified through engineering review rather than inferred from similar-looking equipment.
Describe Loads, Controls, and Protection
List the circuits to be carried forward, including feeder destinations, load descriptions, and any loads that cannot be interrupted. For each protective device, share known frame or trip information, control voltage, trip-unit features, and accessory needs. Identify metering, communications, alarms, interlocks, and control wiring that must interface with plant systems.
Clarify whether existing relaying or control schemes will remain, be revised, or be replaced. Provide available schematics, device settings, point lists, and interface protocols where relevant. Requirements such as selective coordination, arc-energy evaluation, remote operation, or integration with supervisory controls need project-specific review; they should not be presumed included unless defined in the quote scope.
Set the Outage and Installation Boundaries
State the target outage window, permitted shutdown periods, and any sequencing limits. Explain whether temporary power, staged cutover, or partial-lineup replacement is being considered, and identify loads that must remain energized. These constraints help establish a workable scope, but outage duration and installation sequence depend on site conditions and the final approved plan.
Clarify who is responsible for demolition, removal of existing equipment, field connections, testing, commissioning, and restoration. This manufacturer quotes newly manufactured equipment; any site work or existing-equipment handling must be explicitly assigned in the project scope. Coordinate switching procedures, permits, safety planning, and outage authorization with the facility and responsible contractors.
Resolve Open Items Before Release
Separate confirmed facts from assumptions and unanswered questions. A concise list might identify a missing nameplate, unverified bus dimensions, uncertain fault-current data, or a pending utility requirement. Indicate who can verify each item and when. This makes quote clarifications visible and helps avoid treating preliminary information as final design input.
Before equipment is released for manufacture, the responsible engineer should review the proposed configuration, ratings, protection, and interfaces. Coordinate utility requirements and applicable codes with the relevant parties, including the authority having jurisdiction where needed. Final dimensions and connection details should be checked against field conditions, approved drawings, and installation constraints.
Request a Project-Specific Quote
Send the available equipment records, drawings, electrical data, interface details, and outage constraints with the requested delivery location and project schedule. Include the desired scope boundaries and any specification exceptions for review. The manufacturer builds new switchgear and power distribution equipment in the United States using American components, with custom fabrication and nationwide shipping.
Lead time depends on the final configuration, component availability, engineering inputs, and approval process; no schedule should be assumed before project review. Identify whether pricing should cover equipment only or other defined deliverables. A clear request lets the team assess the proposed new lineup, identify missing information, and prepare a quote suited to the retrofit rather than a generic replacement assumption.