Start with project scope and operating context
Begin with the project location, application, requested delivery destination, and the equipment’s role in the distribution system. Note whether the request concerns a new installation, replacement design, expansion, or a planned facility change. Include the desired quotation date and any procurement milestones, while distinguishing firm requirements from preliminary planning assumptions.
Describe the connected facility and operating conditions that affect the scope: normal operating schedule, critical loads, expected future growth, and any planned phases. Identify who will provide design direction and answer technical questions. A clear scope helps the manufacturer identify missing inputs before defining a configuration or preparing a commercial proposal.
Provide one-line diagrams and interface drawings
Submit the latest one-line diagram, with source, transformer, feeder, tie, and load relationships shown as applicable. Include available equipment tags and indicate the intended point of connection. Mark the drawing’s revision and status, such as issued for design or bid, so reviewers can distinguish current information from superseded layouts.
Add plan views, elevations, section details, and connection drawings when available. These can show lineup location, conduit or busway entry, cable termination space, and adjacent equipment. Flag dimensions that are fixed versus preliminary. If drawings are incomplete, state which interfaces remain undecided rather than implying the quotation includes unresolved field coordination.
Organize load schedules and feeder requirements
Provide a load schedule identifying each feeder’s destination, quantity, load type, and known demand or connected load. Note motor loads, large transformers, non-linear loads, and loads with special starting or operating behavior. Where values are estimates, label them clearly and identify the engineer responsible for confirming final demand and diversity assumptions.
For each outgoing circuit, specify the intended protective-device type and relevant requirements, such as frame or trip information when established, adjustable functions, and coordination constraints. Include spare or future provisions as defined by the design. Circuit count alone is not enough to settle space, bus, protection, or termination needs for a quotation.
Confirm system voltage, current, and fault data
State the system voltage, phase, frequency, grounding method, and nominal bus-current requirement for the proposed assembly. Identify the upstream source and provide transformer size and impedance when known. These inputs guide equipment selection, bus arrangement, and device coordination; the responsible engineer should verify that the stated values match the project design.
Request available short-circuit current and the point where it applies, with source assumptions or utility data if available. Identify required short-circuit ratings and any series-rating or selective-coordination criteria specified for the project. Do not assume a rating from a similar installation is transferable; final suitability depends on the actual system and approved design.
Identify the equipment class and construction basis
Specify whether the request is for a low-voltage switchboard, low-voltage switchgear, or medium-voltage equipment, and provide the project’s governing specifications. UL 891 applies to switchboards; UL 1558 applies to low-voltage switchgear. Neither designation should be treated as a medium-voltage standard, so confirm the applicable equipment class and requirements.
Describe configuration preferences that affect the proposal: main and feeder arrangement, breaker or fusible devices, metering, control power, communications, and required compartments or barriers. Treat these as project decisions, not assumed standard features. List specified environmental or seismic criteria, labeling, finish, and documentation requirements, and identify items that need engineering review.
Document installation and site conditions
Provide room dimensions, access routes, floor or housekeeping-pad details, and available working and service clearances. Note door widths, obstructions, ceiling height, and any limitations for moving or setting the equipment. If dimensions are not field-verified, label them preliminary. Installation feasibility depends on the complete route, not only the final lineup footprint.
Describe the installation environment, including indoor or outdoor location, ambient conditions, moisture, dust, corrosive exposure, and elevation when relevant to the specification. State enclosure or ingress-protection requirements only when established by the project documents. Identify cable or busway entry direction and termination constraints, then have the project team confirm these against site drawings.
Include controls, metering, and project interfaces
List required meters, sensors, relays, control circuits, alarms, and communications interfaces, including the intended protocol or signal requirements where known. Attach control schematics, points lists, and network documents if available. Identify whether devices must connect to existing systems and provide relevant interface constraints, rather than assuming compatibility from a device name alone.
Clarify responsibility boundaries for upstream and downstream equipment, field wiring, external control power, and commissioning support. Include applicable specifications for labeling, terminal blocks, and drawings. If the project requires witness activities, special inspections, or particular submittal content, state those requirements early so scope and commercial assumptions can be reviewed.
Set commercial terms and resolve open items
Provide the requested quantity, ship-to location, delivery constraints, requested ship window, and any receiving restrictions. Include the project specification, approved vendor or component requirements if applicable, and required quotation format. The manufacturer builds new equipment in the United States with American components, offers custom fabrication and short lead times, and ships nationwide; confirm project-specific scope and timing.
List requested pricing breakdowns, freight treatment, taxes or exemption documentation, payment terms, quote validity needs, and required submittal milestones. Attach a concise open-items log naming each unresolved decision, its owner, and target resolution date. This makes assumptions visible; the responsible engineer, utility, and AHJ should review applicable design and code requirements.