Map the existing feeder topology
Begin with an up-to-date one-line diagram showing the utility source, campus substations, feeder routes, normally open ties, major loads, and existing protective devices. Confirm actual switch locations and normal operating states in the field; drawings may not reflect later renovations or temporary connections. This map establishes which sections can be isolated without assuming that every campus feeder has an alternate supply.
For a Bowling Green project, document the service voltage, available fault-current information, grounding method, and utility ownership boundary. Identify buildings with critical or time-sensitive loads, planned expansions, and circuits that cannot tolerate an interruption. The responsible engineer should reconcile these facts with utility requirements and site operating procedures before selecting sectionalizing points or requesting equipment pricing.
Choose normal switch positions deliberately
A sectionalizing plan should state the normal position of every relevant switch and tie, including whether a tie is normally open, closed, or controlled under a defined operating procedure. The preferred state depends on load distribution, source capacity, voltage drop, protection design, and the consequences of transferring load. A convenient switching sequence is not sufficient if it violates equipment ratings or operating limits.
Evaluate whether a proposed alternate path can carry the transferred load under expected and contingency conditions. Confirm conductor and bus capacities, transformer loading, voltage regulation, motor-starting effects, and any restrictions imposed by the utility. If a change in switch position changes fault-current contribution or protection reach, include that state in the coordination study rather than treating it as an operational detail.
Define isolation boundaries and work states
For each planned maintenance or fault scenario, identify the device that isolates the affected feeder section and the devices that remain energized. Define boundaries on the one-line and in switching instructions, with attention to backfeed through ties, distributed generation, transformers, and interconnected campus systems. Specify how isolation is verified and how the work area is grounded under the applicable site safety procedures.
Separate equipment selection from the work-control process. Switchgear or switchboard arrangements may provide switching and protective functions, but safe work practices, lockout/tagout, absence-of-voltage verification, and grounding procedures require project-specific planning. Confirm access clearances, cable termination space, operating access, and compartment arrangement with the facility team so the proposed lineup supports the intended isolation method.
Coordinate feeder protection across operating states
Protection coordination must reflect the actual source configuration and every credible switching state. Gather existing relay settings, fuse data, breaker trip information, transformer impedances, conductor data, and utility fault-current values. The engineer can then assess pickup levels, time-current relationships, selective coordination objectives, and whether a feeder fault should be cleared locally or by an upstream device.
A tie that is closed during transfer can change the direction and magnitude of fault current, while a different source may alter relay sensitivity or interrupting duty. Review phase and ground-fault protection, protection of transformers and downstream equipment, and coordination with utility devices. Do not assume existing settings remain suitable after sectionalizing changes; the responsible engineer should approve revised studies and settings.
Select equipment for the service scope
The equipment type follows the electrical service and project design. UL 891 switchboards are low-voltage switchboards; UL 1558 applies to low-voltage switchgear. Medium-voltage equipment is a separate category with distinct design and application requirements. Do not specify a standard from voltage terminology alone: confirm the system voltage, intended use, project specifications, and applicable codes with the engineer and authority having jurisdiction.
A feeder section may call for main, feeder, tie, or other switching functions, but the required arrangement depends on the one-line and operating sequence. Confirm breaker or switch type, bus configuration, metering, control power, protective relays, interlocks, and cable entry direction as applicable. Ratings, construction details, and listed or approved status must be established for the specific design, not presumed from a product category.
Resolve interlocks, controls, and indication
Translate the isolation and transfer plan into a clear control philosophy. Identify which devices are electrically or mechanically interlocked, what permissives are needed, and whether operation is local, remote, or both. Consider how operators will recognize source availability, device position, and abnormal conditions. Interlocking should prevent specified unsafe or unintended operations without blocking legitimate switching steps needed for maintenance or restoration.
Confirm control voltage, communications interfaces, alarm points, and indication requirements with campus operations and any supervisory system integrator. If automatic transfer or remote operation is contemplated, define sensing, logic, fail-safe behavior, and manual fallback expectations. These functions are not universal equipment features; they must be specified, engineered, and checked against the utility interface and the facility’s operating procedures.
Prepare a complete equipment quotation package
A useful quote request includes the one-line diagram, equipment schedule, system voltage, bus and feeder ratings, available fault-current data, grounding details, protection requirements, and applicable project specifications. Provide dimensions, access and cable-entry constraints, environmental conditions, preferred lineup arrangement, and required accessories. Identify what is existing, what is new, and which devices are within the manufacturer’s scope.
Include the intended normal switch positions, transfer states, isolation scenarios, and coordination-study assumptions. State required submittals, inspection or testing expectations, delivery constraints, and the project decision schedule without presuming a particular approval or lead time. The manufacturer can review scope and custom fabrication needs, then identify open technical questions before the equipment configuration is finalized.
Review implementation with local stakeholders
Before release, have the responsible electrical engineer verify equipment selection, fault-duty suitability, protection coordination, and switching sequences. Coordinate utility service conditions and any required utility review, and submit the design to the AHJ where applicable. Facility staff and contractors should validate maintainability, outage windows, labeling, and the practicality of the proposed isolation boundaries for actual campus operations.
For projects in Bowling Green, local site conditions and utility requirements should be confirmed rather than inferred from another campus design. We manufacture new switchgear and power distribution equipment in the United States using American components, offer custom fabrication, short lead times, and nationwide shipping. Final scope, schedule, configuration, and ratings remain subject to project requirements and engineering review.