Start with the system’s highest operating voltage
“35 kV” commonly identifies a nominal system voltage, but equipment selection must use the system’s maximum voltage and the applicable voltage class. Obtain the utility’s voltage criteria and project one-line diagram, then confirm whether the system is grounded, its operating range, and any planned changes that could affect voltage exposure.
Do not assume equipment rated for a nominal 35 kV system is suitable simply because its nameplate figure appears to match. The responsible engineer should compare the equipment’s rated maximum voltage with the system requirements and governing standards. Utility practices and the installation’s actual configuration can affect the required class.
Choose the correct equipment category
Identify the equipment’s function and location before requesting a design: incoming service, feeder switching, transformer protection, sectionalizing or another duty. A 35 kV installation generally calls for medium-voltage equipment, but the required assembly and switching devices depend on the circuit, operating sequence and system design—not the voltage label alone.
Low-voltage switchboards and low-voltage switchgear are not substitutes for medium-voltage equipment. UL 891 applies to switchboards within its scope; UL 1558 applies to low-voltage switchgear within its scope. Neither standard covers 35 kV equipment. Confirm applicable medium-voltage standards, certifications and approvals for the specific design with the engineer and AHJ.
Verify insulation coordination and clearances
Insulation selection must account for the equipment’s maximum voltage and the system’s expected overvoltage stresses. Provide available information on lightning exposure, switching surges, grounding, protective devices and the utility’s insulation-coordination criteria. The engineer uses these inputs to determine required insulation levels and protective-device coordination for the installation.
Ask how the proposed configuration addresses phase-to-phase and phase-to-ground insulation, internal clearances, terminations and cable interfaces. Altitude, contamination, moisture and indoor or outdoor exposure may affect design requirements. These details are project-specific; request confirmation against the applicable standards and installation conditions rather than assuming a particular insulation feature is included.
Establish short-circuit and switching duties
Provide the available fault-current magnitude at the equipment location, the X/R ratio when available, and the utility’s study assumptions. Confirm the required short-circuit withstand and interrupting duties for each device, including the expected clearing time and protective scheme. The selected assembly, breakers and other components must be evaluated for their assigned roles.
Fault duty is not determined by nominal voltage alone. Transformer size and impedance, parallel sources, motors, generators and future system changes can alter fault levels. Distinguish momentary or short-time withstand requirements from a device’s interrupting capability. The responsible engineer should reconcile study results with equipment ratings and protection settings before release for manufacture.
Define the one-line and operating arrangement
A quote-ready one-line should show sources, buses, feeders, transformers, ties, metering and protective devices, with normal and alternate operating conditions identified. Specify the number and purpose of ways, switching requirements, interlocks and any provisions for future circuits. These choices influence the assembly arrangement, component selection, controls and required interfaces.
Clarify whether the system is radial, looped or otherwise configured, and describe who operates the equipment and under what sequence. Identify isolation, grounding and access requirements established by the design. Do not presume a standard lineup will satisfy a project’s operating philosophy; submit control schematics or functional descriptions when they are available.
Account for the installation environment
Document whether installation is indoors or outdoors and provide site conditions relevant to the design, such as ambient temperature range, elevation, humidity, pollution, corrosive exposure and seismic criteria where applicable. Include available room dimensions, cable entry direction, working clearances and access route. These constraints can affect enclosure choices, layout, terminations and installation planning.
Confirm the grounding method, cable types and sizes, termination preferences, conduit or trench approach, and required connection points. Note nearby equipment and any limits on footprint or service access. The manufacturer can review these inputs for a proposed configuration, but the responsible engineer must verify that the completed design meets site, code and utility requirements.
Check standards, interfaces and project documents
List the project specifications, utility requirements, applicable codes and requested documentation with the inquiry. Identify required drawings, nameplate information, operating instructions, wiring diagrams and review milestones. If a particular standard or approval is required, state it explicitly and confirm its applicability to the equipment type and project jurisdiction before treating it as a procurement condition.
Coordinate interfaces with transformers, cables, relays, meters, SCADA and grounding systems. Provide known voltage-transformer and current-transformer needs, control-power source, communications protocols and external connection details. Requirements vary by project and build; confirm each requested feature, rating and deliverable in the approved submittals rather than relying on assumptions from another installation.
Prepare complete information for a build quote
For an accurate quote, send the nominal and maximum system voltage, one-line diagram, fault-study data, equipment function, preliminary ratings, operating sequence and applicable specifications. Add environmental conditions, dimensions, cable and termination details, control and metering requirements, shipping destination, requested schedule and review contacts. Mark unresolved items so assumptions can be identified and addressed.
A U.S. manufacturer building new medium-voltage equipment can review project-specific requirements, provide custom fabrication and arrange nationwide shipping; lead time depends on design scope, component availability and approvals. Before manufacture, have the responsible engineer review the proposed ratings and interfaces, and coordinate utility and AHJ acceptance where required. No selection is complete until project data and final submittals align.